Cathay Pacific Cargo Terminal

Solutions Used for This Case Study

The programme of work was a fundamental building block upon which the whole claim was based. LogiKal were able to review the programme data and work with the team to formulate the best methodology to use under the circumstances.

plane in the sky
Value Added
  • Provide schedule delay analysis service to facilitate Siemens’ claim for EOT against the Main Contractor
  • Conduct a detailed Time-Slice delay analysis of the many Delay Events which occurred during the lifetime of the project
  • Draft several chapters of the EOT claim including sections on an explanation of the methodology and detailed impact of the delays
  • Additional drafting and proof-reading of other sections for consistency and correctness
Airport view of people checking in and plane flying in the background

Heathrow Terminal 2B

LogiKal partnered with Balfour Beatty to drive the development of the vast Terminal 2B at Heathrow. We provided technical expertise and leadership of the programme and project controls function.